Sao Gonçalo Photovoltaic Solar Project (865 MWp) including 500 kV Transmission Line (40 Km.)

2018 / 2021

Country: Brazil | State of Piauí

Client: ENEL Green Power

JGP was responsible por implementation of the E&S programs that were required for the construction phase of the Sao Gonçalo project by the environmental agency. This required mobilizing a resident team to the project site as well as coordination of several monitoring activities that required intermittent field surveys. The E&S programs under JGP responsibility included:

  • Key Flora Species Rescue Program
  • Fauna Rescue Program
  • Fauna Monitoring Program
  • Erosion Monitoring and Control Program
  • Water Quality Monitoring Program
  • Noise Monitoring Program
  • Social Communication and Community Relations Program
  • Environmental Education Program
  • Program for Priority-Hire of Local Workforce 
  • Population Growth and Socio-environmental Indicators Monitoring Program